Contract Amount:
264,575,758,713 IRR
Contract Duration:
9 months
Contract Number and Date:
4305/140/1402 dated August 10, 2023 (19/5/1402 in the Persian calendar)
Site Handover Date:
August 17, 2023 (26/5/1402 in the Persian calendar)
Main Activities Include:
Completion of remaining works on the dam crest
Site development and installation of lighting systems on the dam crest and surrounding area
Completion of permanent buildings including guesthouses and operational facilities
Execution of surveying pillars (micro-geodesy)
River regulation and downstream spillway works
Supply and commissioning of communication systems
Execution and completion of remaining hydromechanical and electrical dam works
Installation of fencing around the dam area and buildings
Work Distribution Based on the Contract’s Attached Bill of Quantities:
Building and structural works: 70.5%
Roads, railways, and airport runways: 13.5%
Mechanical installations: 2.5%
Electrical installations: 1.3%
Dam construction works: 9.5%
Physical Progress:
98%
Status:
At Provisional Acceptance Stage (Temporary Handover)