Execution of Remaining Works for the Main Irrigation and Drainage Network of Abkhor Garan Dam Lands

Execution of Remaining Works for the Main Irrigation and Drainage Network of Abkhor Garan Dam Lands

Contract Title:
Execution of Remaining Works for the Main Irrigation and Drainage Network of Abkhor Garan Dam Lands Related to Civil Units 1 and 2, Including Reservoirs, Pumping Station, and Class 1 & 2 Pipelines and Technical Structures

Contract Duration:
6 months

Contract Number and Date:
5263/140/99 dated September 2, 2020 (12/6/99 in the Persian calendar)

Site Handover Date:
September 23, 2020 (2/7/1399 in the Persian calendar)

Main Activities Include:
This operation encompasses a set of construction and equipment works including:

Execution and completion of the remaining works for the main irrigation and drainage network of Abkhor Garan Dam lands

Completion of reservoirs

Completion of all civil, mechanical, and electrical works of Selsi Olya Pumping Station

Execution of remaining works for Class 1 and 2 pipelines along with technical structures in Civil Units 1 and 2

Work Distribution Based on the Contract’s Attached Bill of Quantities:

Building and structural works: 2%

Roads, railways, and airport runways: 16%

Mechanical installations: 2%

Electrical installations: 10%

Irrigation and drainage: 6%

Power distribution: 3%

Physical Progress:
100%

Status:
Provisional Acceptance (Temporary Handover)